Two new racks in Amsterdam — and what they change

On 21 October we cut Vienna and Copenhagen over from rented edge capacity to routers we operate ourselves. Both locations have been carrying customer traffic since, and the two new racks in AMS2 are now live. Nothing about your configuration needs to change.

What we turned up

The short version:

  • Two additional racks in AMS2, each with A+B power and separate fibre paths to the meet-me room.
  • 2 × 100G uplinks from the new racks to our Amsterdam core.
  • VIE1 and CPH1 now terminate on Atlantika routers instead of a partner's equipment.
  • New private circuits from Amsterdam to Vienna and Copenhagen, with London retained as a secondary path.

The longer version involves a very warm riser, a fibre pull that took longer than the rack build, and a label printer that ran out at the least convenient moment. The invoice is less interesting than the lesson: never schedule a cutover on the same day as a hardware delivery.

Why Amsterdam, again

AMS2 is already our European peering hub. Adding racks there gives us room for the compute expansion planned for 2027 without spending the next year apologising for capacity. The alternative was another rented suite in Frankfurt, which would have added latency and cost without adding resilience.

It also means we can terminate private network attachments in Amsterdam without hairpinning traffic through London. For customers running services in both cities, that is a small but real improvement in both directions.

What customers will notice

  • Vienna and Copenhagen see slightly lower median latency from London, and noticeably steadier jitter between 18:00 and 23:00 UTC.
  • New private network attachments can land in Amsterdam directly.
  • Existing IP addresses, routes and DNS records are unchanged.
  • The status page will show the old edge circuits as retired rather than failed once the billing period ends.

If you have monitoring that alarms on traceroute changes, you may see the new path appear. That is expected; the destination did not move.

What is next

In the first quarter of 2027 we will add a second path into Manchester and upgrade the Dublin edge router. After that, the last rented edge circuit disappears from the estate. Each window will be posted on the status page at least five working days ahead, with a rollback plan and a named owner.

If you want the detailed latency data, it is in the monthly customer report. If you want to argue about our choice of router vendor, email Tom. He enjoys that.